6×4 m pergola – plans, timber list and sizes

A 6×4 m pergola with an open roof: top rafters 45×145 on beams 45×145 and 6 braced posts 95×95. All in pressure-treated C24 timber in standard lengths.

Frame drawing: 6×4 m pergola
Frame drawing · 6×4 m pergola · Download drawing (PNG)

Quick facts

Area
24.0 m²
Beams
45×145
Posts
6 × 95×95
Top rafters
45×145 c/c 900
Footings
6
Boards
21
Total timber
97 m

Member sizes

MemberSizeUtilisationGoverning
Top raftersspan 3.88 m · c/c ≤ 900 mm · open roof, nominal 0.4 kN/m² · g 0.07 kN/m, q 0.36 kN/m 45×145 c/c 900 70% deflection
Beams2 rows · span 2.94 m between posts · g 0.18 kN/m, q 0.90 kN/m 45×145 100% deflection
Postslength 2.40 m · N 3.2 kN (G+Q) · braced, Lef = L 95×95 13% buckling

Timber list

QtySizeLengthTreatment
1 45×95 5.4 m Pressure treated NTR/AB
1 45×95 5.1 m Pressure treated NTR/AB
1 45×95 4.8 m Pressure treated NTR/AB
11 45×145 4.8 m Pressure treated NTR/AB
4 45×145 3.6 m Pressure treated NTR/AB
3 95×95 4.8 m Pressure treated NTR/AB

FAQ

How big do the beams need to be?

The beams are 45×145. Always join beams over a post.

What rafters do I need for a 6×4 m pergola?

45×145 at 900 mm c/c in snow zone 2.0. In snow zone 3.0 you need at undefined c/c.

How much timber does it take?

The frame takes 21 boards in standard lengths, 97 m of timber in total. The cut list is optimised to keep offcuts small.

How many footings do I need?

6 footings. The most heavily loaded one carries 3.2 kN, which on firm friction soil means a footing of roughly Ø300–400 mm.

Do I need a building permit?

Over 15 m² the building no longer counts as a friggebod (permit-free outbuilding). It then usually needs an attefall notification or a building permit. Ask your municipality.

Similar plans

All plans → · Markdown version

The calculations are a design aid based on a simplified Eurocode 5. Connections, foundations and stability must be checked on site – have a structural engineer review the design if a permit is required.